C04006 Project Management

0 Download5 Pages / 1,085 Words

Course Code: C04006
University: University Of Technology Sydney

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Question:

A 1.Research the organisation’s legal obligations regarding projects using at least three sources. Write 150 words summarising how it may be applied during a project.
2.Complete or update two routine pieces of workplace documentation. Use clear, industry-specific terminology, and appropriate structure/format.
3.Communicate one piece of relevant information to a group of people involved in a project or other learners. This should last at least five minutes.
Then, answer at least two questions and ask at least two questions to elicit views and opinions of others on the information.4.Using available mathematical information, measure a project’s work outputs against the projection. (This may be scheduling, budgetary or information.)
If your organisation doesn’t have this mathematical information available, the assessor will provide it instead.
5.Research any relevant organisational policies and procedures and legislative requirements for a routine workplace task relating to each of the following:
Negotiating workPlanning workUndertaking work.
Complete the tasks in line with the requirements and your own responsibilities. 
6.Create a plan to communicate three different pieces of information regarding a project to different groups. For each, identify:
Method of communicationPerson to deliver information.
These should be suitable for the audience, purpose and other contextual factors. 
7.For a routine activity that requires two or more people, collaborate with another employee or learner and contribute to the activity. 
If no collaborative tasks are available, the assessor should set one. 
8.Create a plan for the project which sequences and schedules at least five tasks. 
This could be in the form of a Gantt chart.
9.For one recent outcome of a project, reflect on it and suggest three opportunities for improvement.
B1.In a workplace or simulated workplace environment, work with others to plan and document a project based on organisational parameters.
You must provide valid and reliable evidence of the following tasks:
Identify and clarify project initiation documentation where requiredEstablish relationship between the project and broader organisational strategies and goaAssist in negotiating and documenting project objectives, outcomes and benefitsAssist in establishing the project governance structureAssist in drafting a project charter for approval.
2.In a workplace or simulated workplace environment, complete and update all relevant documentation.
You must provide valid and reliable evidence of the following tasks:
Support breakdown of project objectives into achievable project deliverablesAssist in identifying project stages, and key requirements for stage completionIdentify project milestones and map clearly against time and objectivesAssist in consolidating associated plans and baselines in project management planSupport negotiation with relevant stakeholders and project authority to gain approval of project plan.
3.In a workplace or simulated workplace environment, examine impact that project changes could have on final outcomes.
You must provide valid and reliable evidence of the following tasks:
Maintain and update records against project deliverables and plans at required intervalsPrepare status reports on project progress and identified issuesAssist with undertaking an impact analysis of proposed changes to the projectMaintain relevant project logs and registers accurately and regularly to assist with project auditUpdate associated plans to reflect project progress against baselines and approved changes.
 
4.In a workplace or simulated workplace environment, undertake project finalisation activities.
You must provide valid and reliable evidence of the following tasks:
Assist with project finalisation activities where requiredPrepare project products and associated documentation for handover to clientAssist in completing financial, legal and contractual obligations where requiredContribute perspectives on project performance to assist with project review assessments.

Answer:

Part A
1. Usefulness of using legal obligation
During the design and development of any project the organizations are required to follow specific legal obligations. A project would face major issues if they fail to follow Trade Practice Act 1974 that was outmoded by the competition and consumers ACT launched in 2011, 1st January and it is the content of Australian Consumer’s Law.
It provides standard form of consumer’s contracts with a guaranteed consumer right law while they buy products or avail services from the organizations. It contains rules of lay by agreement and also provides a national level safety law and enforcement systems. Moreover, the legal obligations guide the project team members to conduct a fair business level practice, advertisement practices and marketing practices. Apart from this, a large project can obtain brand identity if they follow the legal obligations. It provides transparency, high privacy, and secured payment methods while confirming transaction.

2 Routine pieces of Workplace documentation

2.2.1 Woolworths Limited:
Woolworths Limited principle and policies

Safety and health policy

Contract level documentation

Work, health and safety documentation- principle contract and trade contract

Safety induction modules

Office contractors (Sept 2016: version)
Energy providers (July 2014: Version)
Merchandisers and demonstrators (Sept 2013: version)

2.2.2 Workplace documentation of ABC private limited
Policies

Disease prevention strategies
Government relation policy
Global anticorruption policies

Human right statements

Non-discriminated healthcare services for the associates
Photos and video usage policies

The project chosen for Woolworths Limited is design and development of one module of ERP system (Supply Chain Management system). How SCM will help to establish a successful interactive platform between the suppliers and buyers will be communicated. In order to design, develop and implement a successful project outcome the mission, vision, strategies and the concept proposal for that particular project will be discussed with the project sponsors to calculate the actual financial measurement that is needed. Apart from this, aim, goal and project objectives will be discussed to the project team members.

Question 1: what are the benefits of SCM system in business decision making?
Question 2: How the business efficiency will increase though this approach?
4. Measuring project’s work outputs

WBS

Task Name

Duration

Resource Names

Cost

0

Schedule for SCM implementation

46 days

 

$254.00

1

   Designing statement of work for SCM design

6 days

Project manager

$30.00

2

   Assigning project team

8 days

Project manager

$30.00

3

   Project prototype design

5 days

designer

$25.00

4

   Milestone 1: Project prototype outline submission

0 days

 

$0.00

5

   Simulation

6 days

system developer

$22.00

6

   Prototype testing

6 days

tester

$20.00

7

   Milestone 2: Completion of project testing

0 days

Project manager

$30.00

8

   Database connectivity

5 days

designer, system developer

$47.00

9

   Final SCM project acceptance testing

5 days

tester

$20.00

10

   Final implementation of the SCM project

5 days

Project manager

$30.00

5. Research any relevant organizational policies and procedures
Negotiation work: This is the most appreciable way that helps Woolworths Limited to accomplish all needful project outcomes fairly. In other words, negotiation is a dispute resolving process or procedure of setting business deals.
Planning work: Before initiating the SCM development project the input and expected outcomes from the project should be planned accordingly.
Undertaking work:  For accomplishing the SCM implementation project the large project should be divided and distribute among the team members according to their skills and knowledge.
6. Communication plan

Piece of information

Method of communication

Person to deliver information

Project status/progress report

Email, PPT and face to face meeting

Project manager

Conflict resolving policies

Email, PPT and face to face meeting

HR manager

7. Routine activities

Immediate checking the current status of the project
Feedback gathering from internal consumers
Change management planning and implementation

8. Creating a project plan

WBS

Task Name

Duration

Start

Finish

0

Schedule for SCM implementation

46 days

Mon 11/12/18

Mon 1/14/19

1

   Designing statement of work for SCM design

6 days

Mon 11/12/18

Mon 11/19/18

2

   Assigning project team

8 days

Tue 11/20/18

Thu 11/29/18

3

   Project prototype design

5 days

Fri 11/30/18

Thu 12/6/18

4

   Milestone 1: Project prototype outline submission

0 days

Thu 12/6/18

Thu 12/6/18

5

   Simulation

6 days

Fri 12/7/18

Fri 12/14/18

6

   Prototype testing

6 days

Mon 12/17/18

Mon 12/24/18

7

   Milestone 2: Completion of project testing

0 days

Mon 12/24/18

Mon 12/24/18

8

   Database connectivity

5 days

Tue 12/25/18

Mon 12/31/18

9

   Final SCM project acceptance testing

5 days

Tue 1/1/19

Mon 1/7/19

10

   Final implementation of the SCM project

5 days

Tue 1/8/19

Mon 1/14/19

9. Opportunities to the project

It will give high rate of business efficiency to reduce cost effects
It will raise the business outputs by boosting cooperation and lowering the delay in processes.
It also enhance the overall network of supply chain

Part B
1. Planning and documenting a project
With the development of top level project planning documentation a project initiation document can be created. Though, for physical logistic operations involved to multiple agencies the identification and clarification of initiation documentation is required by Woolworths Limited. In order to implement SCM system the company should establish contract with the vendors (software) and supplier (hardware). The main objective of the company is to increase the business efficiency by establishing relationship with the suppliers directly. The project will be conducted under the supervision of assigned project manager and system designer.
2. Documentation
The main project deliverable should be divided into small phases and assigned to different stakeholders. The phases to be followed accordingly by the project manager and team members include project initiation, planning, execution, monitoring and closure. However, before final implementation of the project the project manager should give approval to the plan.
3. Examine impact that project changes could have on the outcomes
During the ongoing phase of the SCM implementation project, scope may cause over allocation of time and overrunning budget. However, before final implementation the internal consumers will be interacted to identify the needful modifications. The change management activities should consider those factors. The final outcome can be impacted either positively or negatively by the change management project. Sudden change can cause internal conflicts, managerial and functional issues. Regularly the project status should be assisted and the plan needs to be updated accordingly.
4. Project finalization activities
The financial, legal and contractual obligations should be considered by the project managers to the supplier companies or software vendors to avoid future conflicts. Before finalizing the project the activities that are to be kept in mind include release of the project team, final payment accomplishment, post project evaluation, risk mitigation approaches, measuring consumers satisfaction and schedule and budget management plan. Lastly, the project manager and the executive of Woolworths Limited need to approve the project.  

Free Membership to World’s Largest Sample Bank

To View this & another 50000+ free samples. Please put
your valid email id.

E-mail

Yes, alert me for offers and important updates

Submit 

Download Sample Now

Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.

UploadUnique Document

DocumentUnder Evaluation

Get Moneyinto Your Wallet

Total 5 pages

PAY 3 USD TO DOWNLOAD

*The content must not be available online or in our existing Database to qualify as
unique.

Cite This Work
To export a reference to this article please select a referencing stye below:

APA
MLA
Harvard
OSCOLA
Vancouver

My Assignment Help. (2021). Project Management. Retrieved from https://myassignmenthelp.com/free-samples/c04006-project-management/schedule-and-budget-management-plan.html.

“Project Management.” My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/c04006-project-management/schedule-and-budget-management-plan.html.

My Assignment Help (2021) Project Management [Online]. Available from: https://myassignmenthelp.com/free-samples/c04006-project-management/schedule-and-budget-management-plan.html[Accessed 18 December 2021].

My Assignment Help. ‘Project Management’ (My Assignment Help, 2021) accessed 18 December 2021.

My Assignment Help. Project Management [Internet]. My Assignment Help. 2021 [cited 18 December 2021]. Available from: https://myassignmenthelp.com/free-samples/c04006-project-management/schedule-and-budget-management-plan.html.

×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}

×

Thank you for your interest
The respective sample has been mail to your register email id

×

CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.

Account created successfully!
We have sent login details on your registered email.

User:

Password:

MyAssignmenthelp.com had been helping students from a very long time with meeting specific assignment writing requirements. Even the brightest students require help during the time when they are on bed rest, but at the same time, they do not want their grades to fall behind. Our assignment assistance is available for 24*7 to cater to your requests like Who can provide the best assignment help in Sydney?

Latest Management Samples

div#loaddata .card img {max-width: 100%;
}

MPM755 Building Success In Commerce
Download :
0 | Pages :
9

Course Code: MPM755
University: Deakin University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers:
Introduction
The process of developing a successful business entity requires a multidimensional analysis of several factors that relate to the internal and external environment in commerce. The areas covered in this current unit are essential in transforming the business perspective regarding the key commerce factors such as ethics, technology, culture, entrepreneurship, leadership, culture, and globalization (Nzelibe, 1996; Barza, 2…
Read
More

SNM660 Evidence Based Practice
Download :
0 | Pages :
8

Course Code: SNM660
University: The University Of Sheffield

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: United Kingdom

Answers:
Critical reflection on the objective, design, methodology and outcome of the research undertaken Assessment-I
Smoking and tobacco addiction is one of the few among the most basic general restorative issues, particularly to developed nations such as the UK. It has been represented that among all risk segments smoking is the fourth driving purpose behind infections and other several ailments like asthma, breathing and problems in the l…
Read
More
Tags:
Australia Maidstone Management Business management with marketing University of New South Wales Masters in Business Administration 

BSBHRM513 Manage Workforce Planning
Download :
0 | Pages :
20

Course Code: BSBHRM513
University: Tafe NSW

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Task 1
1.0 Data on staff turnover and demographics
That includes the staffing information of JKL industries for the fiscal year of 2014-15, it can be said that the company is having problems related to employee turnover. For the role of Senior Manager in Sydney, the organization needs 4 managers; however, one manager is exiting. It will make one empty position which might hurt the decision making process. On the other hand, In Brisba…
Read
More

MKT2031 Issues In Small Business And Entrepreneurship
Download :
0 | Pages :
5

Course Code: MKT2031
University: University Of Northampton

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: United Kingdom

Answer:
Entrepreneurial ventures
Entrepreneurship is the capacity and willingness to develop, manage, and put in order operations of any business venture with an intention to make profits despite the risks that may be involved in such venture. Small and large businesses have a vital role to play in the overall performance of the economy. It is, therefore, necessary to consider the difference between entrepreneurial ventures, individual, and c…
Read
More
Tags:
Turkey Istanbul Management University of Employee Masters in Business Administration 

MN506 System Management
Download :
0 | Pages :
7

Course Code: MN506
University: Melbourne Institute Of Technology

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
An operating system (OS) is defined as a system software that is installed in the systems for the management of the hardware along with the other software resources. Every computer system and mobile device requires an operating system for functioning and execution of operations. There is a great use of mobile devices such as tablets and Smartphones that has increased. One of the widely used and implemented operating syste…
Read
More
Tags:
Australia Cheltenham Computer Science Litigation and Dispute Management University of New South Wales Information Technology 

Next

Need an essay written specifically to meet your requirements?

Choose skilled experts on your subject and get an original paper within your deadline

156 experts online

Your time is important. Let us write you an essay from scratch

Tips and Tricks from our Blog

11174 Introduction To Management

Free Samples 11174 Introduction To Management .cms-body-content table{width:100%!important;} #subhidecontent{ position: relative; overflow-x: auto; width: 100%;} 11174 Introduction

Read More »