Question:
Your firm has been awarded the Program Management contract for the design, permitting, construction and activation of a natural compressor station in south west New York State. A natural gas pressure station increases the pressure along a natural gas pipeline. Your company’s scope of work will include the following tasks:1. Selecting a design engineer2. Selecting an environmental consultant that will prepare the federal and state permit applications3. Maintain the project schedule4. Property Acquisition5. Procuring the long lead time equipment6. Bidding and negotiating construction contracts7. Managing the Construction of the Facility8. Commissioning the facility
The Owner has budgeted a total of $33,500,000.00 for the project and the facility must be put into service 30 months after your firm has been given the notice to proceed, which will be December 1, 2018. This facility will generate $10,000 a day in revenue for your client. Your client will have to pay a contractual penalty of $5,000 per day to its customers if the schedule is exceeded until the facility is placed into service.You are to allocate the $33,500,000 budget as follows:1. Engineering Design – 10%2. Land Acquisition – 5%3. Permitting (Including Consultant) – 5%4. Long Lead Items – 35%5. Constructiona. Construction Inspection – 5%b. Construction – 30%6. Contingency – 10%Here are the tasks and associated durations that you will base your schedule upon: Selection of the engineering and environmental consultant1. Preparation of RFP’s for the engineering firms and environmental consultant – 30 days following notice to proceed2. Bidding period for engineering firms – 3 weeks3. Negotiation of the consultant’s contracts and issuing the notice to procced for these two contracts– 1 weekAssociated Costs1. Program Management Fees (Your firm): $1,000,0002. Design Engineer: $2,000,0003. Environmental Consultant: $ 650,000Property Acquisition1. Site Selection – 30 days following notice to proceed of your firm2. Due Diligence of selected site – 6 weeks3. Property Closing – 4 weeks
You must make an important recommendation to your client; your firm has identified two suitable properties for the compressor station. Site A will cost $1,300,000.00, Site B will cost $950,000.00 however due to the presence of wetlands, it will take 6 months longer to obtain regulatory permits for Site B. You need to recommend to your client which property to go with based upon schedule and budget considerations.
Answer:
Particulars
Calculation
Cost
Program Management Fees
$10,00,000
Design Engineer
$20,00,000
Environmental Consultant
$6,50,000
Site A
$13,00,000
Real Estate Appraiser Fees
$6,000
Legal Fees
$25,000
Other Professional Fees
$15,000
Utility Upgrade
$7,50,000
Permitting Fees
$5,25,000
Federal Permit Package
$50,000.00
State Permit Package
$1,00,000.00
Municipal Permit Package
$75,000.00
Attorney fees
$1,50,000.00
Cost of Tree Plantation
$1,50,000.00
Main Turbine Unit cost
$78,00,000
Filter Separators cost
$4,65,000
Large Diameter Valves cost
$9,75,000
Prefabricated Compressor Building cost
$7,45,000
Electrical Motor Control Center and Switch Gear cost
$3,56,000
Large Diameter Piping cost
$1,50,000
Emergency Generator cost
$4,10,000
Fuel Gas Skid cost
$4,85,000
Rough site work
$50,00,000
Foundation for the Compressor Unit
$10,00,000
Foundation of the Compressor Building
$5,00,000
Installation of the Compressor Unit
$2,50,000
Erection of the Compressor Building
$3,50,000
Mechanical Work
$7,50,000
Electrical Work
$11,00,000
Finished Site Work
$2,50,000
Landscaping
$1,00,000
Commissioning and Testing of the Facility the Station
$1,25,000
Drilling crew
$16,50,000
Blasting Crew
$11,00,000
Cost of truck
$57,200
General Contractor Cost
$2,80,720
Local building permits cost
$1,25,000
Contingency
$32,05,080
Total Budget
$3,35,00,000
Area of rock to be excavated
Length
150
50
(in yards)
Breadth
100
33
(in yards)
Deep
6
2
(in yards)
Area
3300
Rock Drilled and Blasted
Resource
Rate
Cost
Rate
15
cubic yards per day
drilling crew
$7,500.00
$16,50,000.00
Days
220
blasting crew
$5,000.00
$11,00,000.00
Trasportation
Rate in hours
Rate in Days
Total cost
cubic yards per trip
10
Cost of truck
65
520
$57,200
Per day trip
3
total cubic yard transported
30
in one day
Total time
110
General Contractor cost
10% of all costs
$2,80,720
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 3 pages
PAY 2 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2021). CE 610 Construction Management. Retrieved from https://myassignmenthelp.com/free-samples/ce610-construction-management/contractual-penalty.html.
“CE 610 Construction Management.” My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/ce610-construction-management/contractual-penalty.html.
My Assignment Help (2021) CE 610 Construction Management [Online]. Available from: https://myassignmenthelp.com/free-samples/ce610-construction-management/contractual-penalty.html[Accessed 18 December 2021].
My Assignment Help. ‘CE 610 Construction Management’ (My Assignment Help, 2021)
My Assignment Help. CE 610 Construction Management [Internet]. My Assignment Help. 2021 [cited 18 December 2021]. Available from: https://myassignmenthelp.com/free-samples/ce610-construction-management/contractual-penalty.html.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
Do not feel confident about producing 100% plagiarism-free content? Avail online assignment help from the experts at MyAssignmenthelp.com. The expert writers on this website perform several measures to ensure all the assignments they produce have zero traces of plagiarism on them. If you want, the website can also provide you with the plagiarism report of the solution. The plagiarism-free assignment is available for all academic tasks across all the major subject areas.
Latest Management Samples
div#loaddata .card img {max-width: 100%;
}
MPM755 Building Success In Commerce
Download :
0 | Pages :
9
Course Code: MPM755
University: Deakin University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers:
Introduction
The process of developing a successful business entity requires a multidimensional analysis of several factors that relate to the internal and external environment in commerce. The areas covered in this current unit are essential in transforming the business perspective regarding the key commerce factors such as ethics, technology, culture, entrepreneurship, leadership, culture, and globalization (Nzelibe, 1996; Barza, 2…
Read
More
SNM660 Evidence Based Practice
Download :
0 | Pages :
8
Course Code: SNM660
University: The University Of Sheffield
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: United Kingdom
Answers:
Critical reflection on the objective, design, methodology and outcome of the research undertaken Assessment-I
Smoking and tobacco addiction is one of the few among the most basic general restorative issues, particularly to developed nations such as the UK. It has been represented that among all risk segments smoking is the fourth driving purpose behind infections and other several ailments like asthma, breathing and problems in the l…
Read
More
Tags:
Australia Maidstone Management Business management with marketing University of New South Wales Masters in Business Administration
BSBHRM513 Manage Workforce Planning
Download :
0 | Pages :
20
Course Code: BSBHRM513
University: Tafe NSW
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Task 1
1.0 Data on staff turnover and demographics
That includes the staffing information of JKL industries for the fiscal year of 2014-15, it can be said that the company is having problems related to employee turnover. For the role of Senior Manager in Sydney, the organization needs 4 managers; however, one manager is exiting. It will make one empty position which might hurt the decision making process. On the other hand, In Brisba…
Read
More
MKT2031 Issues In Small Business And Entrepreneurship
Download :
0 | Pages :
5
Course Code: MKT2031
University: University Of Northampton
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: United Kingdom
Answer:
Entrepreneurial ventures
Entrepreneurship is the capacity and willingness to develop, manage, and put in order operations of any business venture with an intention to make profits despite the risks that may be involved in such venture. Small and large businesses have a vital role to play in the overall performance of the economy. It is, therefore, necessary to consider the difference between entrepreneurial ventures, individual, and c…
Read
More
Tags:
Turkey Istanbul Management University of Employee Masters in Business Administration
MN506 System Management
Download :
0 | Pages :
7
Course Code: MN506
University: Melbourne Institute Of Technology
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
An operating system (OS) is defined as a system software that is installed in the systems for the management of the hardware along with the other software resources. Every computer system and mobile device requires an operating system for functioning and execution of operations. There is a great use of mobile devices such as tablets and Smartphones that has increased. One of the widely used and implemented operating syste…
Read
More
Tags:
Australia Cheltenham Computer Science Litigation and Dispute Management University of New South Wales Information Technology
Next